(a) General. The following information and data shall be prepared by an Indiana licensed professional engineer or land surveyor engaged in stormwater management design for any development, redevelopment, or new construction on real estate which lies within the Town of St. John. These requirements are in addition to the master drainage plan requirements of division 1 of this article, as amended from time to time.

(b) Preliminary Pollution Prevention Plan.

(1) Construction site pollution control plan conforming to 327 IAC 15-5-7 or 15-5-7.5, including, at a minimum:

a. Preliminary sediment and erosion control plan.

b. Location of construction entrance.

c. Location of stormwater outlet or outlets.

(2) Construction site pollution control plan conforming to 327 IAC 15-13-15 including, at a minimum:

a. Preliminary location and estimated size of temporary BMPs.

b. Temporary scrap and waste material storage and ultimate disposal methods.

c. Draft description of proposed self-monitoring program.

(3) Postconstruction pollution control plan conforming to 327 IAC 15-5-6.5 and 15-13-16, including, at a minimum:

a. Preliminary location and estimated size of permanent BMPs.

b. Description of proposed maintenance program.

(c) Pollution Prevention and Control Plan.

(1) Submit the following with the detailed engineering plans for review.

(2) Construction site pollution control plan conforming to 327 IAC 15-5-7 or 15-5-7.5, including, at a minimum:

a. Completed sediment and erosion control plan.

b. Location and details of construction entrance.

c. Location of material stockpiles.

d. Location of stormwater outlet or outlets.

e. BMP practice details for all of above.

(3) Construction site pollution control plan conforming to 327 IAC 15-13-15, including, at a minimum:

a. Location, size, section and details of temporary BMPs.

b. Location of concrete wash out site or sites.

c. Storage location of fuel, lubricant, solvent and other potential pollutants used at the site.

d. Location of scrap and waste material storage and ultimate disposal methods.

e. BMP practice details for all of above.

f. Description of self-monitoring program.

(4) Postconstruction pollution control plan conforming to 327 IAC 15-5-6.5 and 15-13-16, including, at a minimum:

a. Location, size, section and details of permanent BMPs.

b. BMP practice details for each facility type.

c. Description of proposed maintenance program.

d. Description of financial responsibility and assurance for maintenance program.

(5) Copy of the draft NOI to be submitted to IDEM.

(d) Documentation Required During Construction.

(1) Provide copies of notice of violation (NOV) or stop work orders, and any related correspondence with federal, state or county agencies. Provide copies of corrective action plans and/or changes to construction plans resulting from such notices.

(2) Provide copies of self-monitoring reports upon request.

(3) Provide copies of plan changes resulting from field conditions during construction.

(e) Documentation Required Before Acceptance.

(1) Provide copies of notice of termination (NOT) and any related correspondence with federal, state or county agencies.

(2) Provide paper and digital copies of as-built plans prepared according to section 21A-99, as amended from time to time.

a. Permanent drainage, detention or BMPs which will be accepted by the Town shall be clearly identified by color, shading or hatching.

b. Include a certified statement by a professional engineer or registered land surveyor licensed in the State of Indiana on record drawings stating that the completed storm drainage system substantially complies with construction plans as approved.

(3) All such submitted plans shall be reviewed for compliance within thirty (30) days after submission to the Department of Planning and Building or Town Engineer.

(Ord. No. 1432, T. 4, §§ 1—5, 11-16-06)